Design of Electrical Testing Laboratories
CESI,
Milan,
Italy |
CESI Synthetic Facility upgrading on Transformer Limited Fault test with fast transient recovery voltage
|
2019 |
A basic design has been carried out to improve Synthetic Facility in order to perform Transformer Limited Fault test having fast transient recovery voltage on HV circuit-breakers with rated voltage up to 420 kV, in full compliance with clause 5 of IEEE Standard C37.06.1. |
|
|
Tasks performed
|
||
|
CESI,
Milan,
Italy |
CESI Synthetic Facility upgrading on Terminal Fault and Out-of-Phase tests on
HV Circuit-breakers and Earth Fault tests on HV Fast Earthing Switches
|
2019 |
A basic design has been carried out in order to improve CESI Synthetic Facility to perform making operation in:
|
||
Tasks performed
|
||
|
||
|
GCC ETL,
Dammam,
Saudi Arabia
|
Basic and detailed design of a new Testing Laboratory
|
2018 - 2019
|
*
|
|
Testing Facilities and maximum ratings of equipment to be tested |
||||
The Laboratory, supplied by one 3200 MVA generator with provision to add second generator in the future, includes the following testing facility:
|
||||
Tasks performed
|
||||
High Power and Power Transformer Test Bay
|
|
|||
High Voltage, Pollution and Cables Laboratories
|
Temperature Rise and Mechanical Laboratories
|
|||
Synthetic Test Facility
|
|
|||
|
||||
*as CESI subcontractor
CPRI,
Bangalore
,
India |
Augmentation of High Power Test Facilities in Bangalore High Power Laboratory
|
2017
in progress |
* |
|
Testing Facilities and maximum ratings of equipment to be tested |
||||
|
||||
Tasks performed
|
||||
Synthetic Test Facility
|
Transformer Short-circuit Test Facility
|
|||
Temperature Rise Laboratory
|
||||
|
||||
* as CESI partner
CPRI, Hyderabad,
India |
Establishment of a new On line Testing Laboratory at Hyderabad
|
2017
in progress
|
* |
|||||||
Testing Facilities and maximum ratings of equipment to be tested |
||||||||||
|
||||||||||
Tasks performed: for each of the testing facility the following tasks have been performed:
|
||||||||||
|
|
|||||||||
|
|
|||||||||
|
||||||||||
* as CESI partner
ERDA,
Vadodara,
India
|
Basic Design of a new High Power Testing Laboratory
|
2016
|
* |
|
Testing Facilities and maximum ratings of equipment to be tested |
||||
|
|
|||
Tasks performed:
|
||||
|
||||
* as CESI subcontractor
Rosseti,
St. Petersburgh, Russia |
Basic Design of a National Testing Center in Russia
|
2015-2016
|
* |
||
Testing Facilities and maximum ratings of equipment to be tested |
|||||
The Power supply of the Laboratory includes 4 Short-circuit Generator each rated 3500 MVA.
|
|
||||
Tasks performed:
|
|||||
High Power Laboratory
|
High Voltage Laboratory
|
||||
Synthetic Test Facility
|
|
||||
|
|||||
* as CESI partner
KONÄŒAR Electrical Industries,
Zagreb,
Croatia
|
Basic Design of a Testing Laboratory
|
2014-2015 |
Testing Facilities and maximum ratings of equipment to be tested |
||
KONÄŒAR - ElectricalIndustries requested the basic design of a Laboratory able to perform type tests on its catalogue manufactured products and including:
|
||
Tasks performed:
|
||
|
||
|
Noja Power Switchgear,
Brisbane,
Australia
|
Detailed Design of a MV Switches Testing Facility based on Synthetic method
|
2014
|
|
Testing Facilities and maximum ratings of equipment to be tested |
|||
The Testing Facility is addressed to perform single phase mainly active load current switching tests at 100% of the rated current on MV Switches with rated voltage from 15.5 kV up to 38 kV and rated mainly active
switching current from 100 A up to 800 A at 50 Hz and 60 Hz frequency.
The test supply consists of a pre-charged capacitor bank. The discharge of capacitor bank on the reactor bank determines the test current that is broken by the Switch under test: a parallel branch allows to obtain
the Transient Recovery Voltage in agreement with test duty TD load2 of IEC Standard 62271-103 - Table 4.
|
|||
Tasks performed:
|
|||
|
|
||
|
|||
KEMA,
Arnhem,
Netherlands
|
Consultancy engineering services addressed to the commissioning of two 2500 MVA Short Circuit Generators installed at KEMA Laboratory
|
2014-2015 |
Engineering services performed
|
||
In the framework of the supply by Alstom Power to KEMA of two Short-circuit Generators (addressed to supply short-circuit tests in parallel of the already existing four generators)
the following technical assistance during Commissioning has been carried out:
|
||
|
Universidad Del Valle,
Calì,
Colombia
|
Feasibility Study of MV Power TestingLaboratory
|
2014-2015 |
|
Testing Facilities and maximum ratings of equipment to be tested |
|||
|
|||
Tasks performed:
|
|||
|
|||
|
|
||
Expert System,
Russia
|
Feasibility Study for a new Federal Testing Center
|
2013-2014 |
A comprehensive feasibility study has been carried out in supporting the decision by the Russian Federal Grid company (now Rosseti) on the establishment of a Federal Testing Center able to test High Voltage
electrical equipment.
On the basis of the following developed outputs:
the study demonstrated that a powerful Testing Center can really determine the improvement of the domestic electromechanical sector and the overcoming of the technological gap which ultimately increase the electrical
tariffs and hampers the country economic growth.
A complete Business Plan has been evaluated taking into accountcapital expenditure, revenues, staff wages, operating costs, profit & loss plan for a Federal Testing Center
including the following testing facilities:
Finally a Federal Testing project financinghas been proposed.
|
||
|
Alstom,
Lyon,
France
|
Detailed Design of CERDA High Power Synthetic Laboratory
|
2013-2014 |
* |
Testing Facilities and maximum ratings of equipment to be tested |
|||
Starting from the results of the Basic Design performed at 2011-2013 the detailed design of the testing facility has been developed to perform short-circuit and capacitive switching tests up to the following maximum
ratings of the equipment to be tested:
|
|||
Tasks performed:
|
|||
|
|||
|
* as CESI subcontractor
Hyundai Heavy Industries,
South Korea
|
Basic Design of an High Power Laboratory
|
2013-2014 |
* |
Testing Facilities and maximum ratings of equipment to be tested |
|||
|
|||
Tasks performed:
|
|||
|
|||
|
* as CESI subcontractor
Alstom Power,
Milan,
Italy
|
Modelling of the parallel operation of Generators in Short-circuit tests
|
2012 |
Engineering services performed
|
||
In the framework of Alstom Power proposal to KERI (Korea Electrotechnology Research Institute) of two Short-circuit Generators for a total short-circuit power of 4800 MVA addressed to supply short-circuit tests in
parallel of the already existing 4800 MVAGenerator, it has been developed a simulation tool of synchronous generators, including driver, used in short circuit tests.
The model, developed in cooperation with the Electrical Engineering Department of the University of Pavia, allows the simulation of the drive-generator system in three-phase and single-phase systems at 50 Hz and 60
Hz, with and without excitation in a temporal transient of 150 ms from the short circuit start, providing the generator status at the beginning and end of the transient and the power flows in the different
configurations.
The model also simulates the operation of 2 or 3 generators feeding short-circuit tests, in particular for the paralleling procedure and the configuration of the protections.
On the basis of the results of the simulations carried out, the required operating conditions (maximum excitation current required, minimum current limiting reactances to be connected in series with the Generators,
maximum faults currents, etc.) for an effective parallel operating conditions in three or single phase short-circuit tests, at full power, at 60 Hz and 50 Hz, have been defined.
|
||
|
LS Electric,
Busan,
South Korea
|
Basic and detailed design of High Power Synthetic Testing Laboratory of HVDC Thyristor Valves
|
2012-2013 |
Testing Facilities and maximum ratings of equipment to be tested |
||
In the framework of the establishment by LS Electric of a new Testing Facility for operational electrical tests on HVDC Thyristor Valves with max voltage of 30 kV and max current of 2500 A a review of the Basic and Detailed design of the Facility has been carried out. The performed tests are based on Synthetic method replicating the switching stresses on the valves in operation, in full agreement with IEC Standard 60700-1. |
||
Tasks performed:
|
||
|
||
|
Turkish Standard Institute,
Turkey
|
Feasibility Study of LV/MV/HV Testing Laboratory Complex
|
2012-2013 |
* |
Testing Facilities and maximum ratings of equipment to be tested |
|||
The Turkish Institute of Standard requested a feasibility study concerning the establishment of an independent Testing Laboratory complex in Turkey to support the domestic electromechanical industries and power
utilities. The complex includes the following Testing Facilities:
|
|||
Tasks performed:
|
|||
|
|||
|
* as CESI subcontractor
KERI,
Changwon,
South Korea
|
Consultancy engineering services on detailed design of 4000 MVA High Power Laboratory
|
2012-2013
|
Testing Facilities and maximum ratings of equipment to be tested |
||
KERI extended its High Power Testing Laboratory with a new section in order to increase testing capabilities up to 4000 MVA short-circuit power through installation of a second Short-circuit Generator, new
Short-circuit Transformers and the rearrangement of the power circuits supplying the different test bays.KERI requested a review of some detailed design
Technical Specification.
|
||
Tasks performed:
|
||
|
||
|
NHPTL,
Bina,
India
|
Engineering services relating to the construction of Power Transformer Testing Laboratory
|
2012-2013 |
* |
Testing Facilities and maximum ratings of equipment to be tested |
|||
On the basis of the design developped in 2010 year the National High Power Testing Laboratory erected the Power Transformer Testing Laboratory supplied by three incoming lines
at 765 kV, 400 kV and 220 kV and including two test sections:
NHPTL require engineering services supporting the different phases of the Laboratory construction.
|
|||
Tasks performed:
|
|||
|
|||
|
Alstom,
Lyon,
France
|
Technical Assistance to the Revamping of CERDA High Power Laboratory
|
2011-2013 |
* |
Testing Facilities and maximum ratings of equipment to be tested |
|||
The Feasibility Study and Basic Design concerning the renovation and upgrade of the Synthetic facilities was addressed to achieve the following performances:
|
|||
Tasks performed:
|
|||
|
|||
|
* as CESI subcontractor
State Grid Electrical Power Research Institute,
China
|
Basic design of a new High Power Testing Laboratory
|
2011-2012 |
* |
|
Testing Facilities and maximum ratings of equipment to be tested |
||||
The High Power Testing Laboratory, is a new section of the State Grid Inspection & Testing Center in Changzou which already includes a AC/DC High Voltage Test Hall and an Environment and Mechanical Test Hall.
The High Power Testing Laboratory, supplied by a multi-generator group (two 3200 MVA generators with provisions to add a third generator in future) and a HV substation fed from the 220 kV network, includes the
following testing facilities:
|
||||
Tasks performed:
|
||||
Basic Specification for HV Direct and Synthetic tests:
|
Basic Specification of Medium Voltage Laboratory:
|
|||
|
||||
* as CESI subcontractor
TECNALIA,
Bilbao,
Spain
|
Engineering services for the contruction of a new High Power Laboratory
|
2011-2012 |
* |
Testing Facilities and maximum ratings of equipment to be tested |
|||
The Laboratory, located in the Parque Tecnologiquo Bizcaia, includes the following Testing Facilities:
|
|||
Tasks performed:
|
|||
|
|||
|
* as CESI subcontractor
State Grid Electrical Power Research,
India
|
Feasibility study and Basic design for a new On-Line Short-circuit Testing Laboratory
|
2010 |
* |
Testing Facilities and maximum ratings of equipment to be tested |
|||
The Laboratory will be supplied by the High Voltage Network at 765 kV and 400 kV and includes the following Testing Facility:
|
|||
Tasks performed:
|
|||
|
|||
|
* as CESI subcontractor